LODAR. July 16. KAZINFORM /Vera Livintsova/ Modern materials are used for reconstruction of collectors and water carriage systems in Pavlodar; Kazinform reports.
None
None

According to the Road Map Program reconstruction of the main collector in Lermontov Street with the length of 350 meters is underway. Here the reinforced concrete pipes will be replaced with glass-plastic pipes that will increase carrying capacity and let use the system during 50 years.

The reconstruction of the water carriage system is also carried out in Dimitrov and Tolstoy Streets.

655 people work at three facilities whereas 80 per cent of them were unemployed. The reconstruction will be completed in November.