Number of RES projects in Kazakhstan increases

NUR-SULTAN. KAZINFORM Today, at the Government’s sitting, Vice Minister of Energy Makhambet Dosmukhambetov reported about the situation on introduction of renewable energy sources in Kazakhstan.

photo: QAZINFORM

«Since the year beginning we have commissioned 14 renewable energy generating projects with the capacity of 402MW. 4 new projects with the capacity of 104.8MW will be implemented by the end of 2019,» said the Minister.

In his words, in 9 months of 2019, the volume of energy generated by RES was 1.7bn kWh that is 65% more compared to the same period in 2018. «The share of RES in electricity generation is around 2% (2.3% as per 2019 plan),» the speaker noted.

«In general, the number of RES projects across the country in 2019 increased by 20: from 67 to 87. Their total capacity increased by 1.9fold: from 537MW in 2018 to 1042MW in 2019,» the Vice Minister added.