PETROPAVLOVSK. KAZINFORM - Reconstruction of the Sokolovsky group water supply system is about to complete in northern Kazakhstan.
KZT 4.5 billion was allotted from the republican budget for reconstruction of the water supply system that started back in January 2011. The Almaty-based company Caspian Constractors Trust LLP was named as one of the contractors for the project.
The reconstructed waterline will supply 13 villages with water, according to Serik Sharipov of Caspian Contractors Trust.
The project is set to be commissioned in December 2014.
Construction of the new Presnovsky water supply system is expected to start in the region soon.